Traffic Update: Coachline Boulevard Reconstruction

Screen Shot 2019-01-30 at 3.19.36 PM.png

Coachline Boulevard Reconstruction – from Twin Peaks Road south to Silverbell Road and from Twin Peaks Road north to Silverbell Road

The Town of Marana and their contractor, Sunland Asphalt Construction Inc., have begun work to replace curb, sidewalks, and repair drainage issues at the intersection of Silverbell Road and Coachline Boulevard/Continental Reserve Loop. Work is expected to be completed by mid-February 2019.

Motorists, pedestrians and bicyclist traveling through the area should plan for the following:

  • Travel will be reduced to one-lane in each direction. This traffic control will remain in place through mid-February 2019.

  • All turn movements will be permitted, however dedicated turn lanes may be restricted.

  • Portions of sidewalks will be closed during removal, replacement and while the concrete cures.

  • All business access will be maintained.

In preparation of the upcoming paving operation scheduled for late February, the contractor will begin milling (removing) the asphalt along Coachline Boulevard from Twin Peaks Road south to Silverbell Road.

  • There will be temporary side street closures as equipment moves through the work area.

  • All business access will be maintained.

  • The milling operation is scheduled to begin in mid-February 2019.