The various projects on Tangerine have had some slight schedule changes. A few are running a little long, while some will end faster than expected. Here is the latest update.
The project to work on waterlines on Camino de Oeste south of Tangerine Road will last until Friday, August 4. During this work, traffic will be shifted around the work area, allowing one lane in each direction. Resident access will be maintained during construction. Traffic control will be in place 24 hours a day.
Paving on Tangerine continues through Thursday, August 3 from 6 a.m. to 4 p.m. each day. The contractor is ahead of schedule paving the new westbound lanes of Tangerine Road from Tangerine Crossing Drive to La Cholla Boulevard. Beginning Wednesday August 2nd, paving will begin on side street entrances on the north side of Tangerine Road from Tangerine Crossing Drive to La Cholla Boulevard. Side streets will be intermittently closed as paving equipment progresses through the area. Please expect delays.
Beginning Wednesday, August 2nd, from 5:30 am - 3:00 pm, the southbound La Cholla left turn lane onto eastbound Tangerine will be closed. Left turns can be made from the southbound through lane. Watch for signage.
Beginning Thursday, August 3rd, from 5:30 am - 3:00 pm, the northbound La Cholla left turn lane onto westbound Tangerine will be closed. Left turns can be made from the northbound through lane. Watch for signage.